MJR 2021-001 CO
Major Modification (PD)PHASE 1-AREA ‘A’
The applicant wants to build a clubhouse and four apartment buildings containing 260 units on vacant land in Area 'A' of an approved planned development. If approved, this apartment complex would be developed on land currently zoned for mixed-use commercial purposes.
Read the staff report this summary came fromCase details
- Location
- South side of U.S. Hwy 64; +/-897.20 feet east of Reid Hooker Road
- Jurisdiction
- Unincorporated Shelby County
- District
- District 2
- Next step if approved
- Proceeds to the Shelby County Board of Commissioners.
Case history
April 8, 2021
Land Use Control Board — held case
Staff recommendation: Approval with conditions
This matter was held in abeyance by the board for a period of one month during its March 11, 2021, meeting
Source documentMarch 11, 2021
Land Use Control Board — correspondence case
Staff recommendation: Hold
one (1) month
Source document
Sources
Every case detail on this page — dates, districts, parcels, staff recommendations — is read directly from the public documents below. The only exception is the summary at the top, which is AI-generated and labelled as such.
- https://www.shelbycountytn.gov/Archive.aspx?ADID=10213
- https://www.shelbycountytn.gov/Archive.aspx?ADID=10112
Something here look wrong? Report an error on this page.