Memphis Zoning Watch

Two-year time extension for 155 Foot CMCS tower now modified to 122 feet in height.

AI-generatedPlain-English summary — always check the source document.

The applicant seeks a two-year extension to build a cell tower that was originally approved at 155 feet but is now proposed at 122 feet in height on approximately 5.0 acres. If approved, the applicant will have additional time to complete the project and related subdivision requirements.

Read the staff report this summary came from

Case details

Location
8199 E. Holmes Rd.
Applicant / owner
Mr. Rickey Greer/Verizon Wireless
Next step if approved
Proceeds to the Shelby County Board of Commissioners.

Case history

  1. January 11, 2024

    Land Use Control Boardcorrespondence case

    Staff recommendation: Approval with conditions

    Source document

Sources

Every case detail on this page — dates, districts, parcels, staff recommendations — is read directly from the public documents below. The only exception is the summary at the top, which is AI-generated and labelled as such.

Something here look wrong? Report an error on this page.